Period-End Closing - Projects (BNA)

Period-End Closing - Projects (BNA)

During settlement, costs incurred under the primary and secondary cost (including overhead cost via costing sheet) elements by a sender are allocated to one or more receivers. When you settle by cost element, you settle using the appropriate original cost element.

An allocation structure consists of one or several settlement assignments. An assignment shows which costs (origin: Cost element groups from debit cost elements) are to be settled to which receiver type (for example, cost center, order, and so on).

In the settlement profile, you define the range of control parameters for settlement, and the strategy for the automatic generation of settlement rules. Finally, you execute the settlement and the project is settled to the responsible cost center.

In addition to internal projects, this scope item also covers period-end steps for Assets under Construction (AuC). During the construction phase of an asset, all actual postings are assigned to the AuC. Once the asset is complete, the next project settlement run transfers the AuC asset value to the completed asset.

Key Process Steps Covered

  • Run actual overhead - projects
  • Perform the period end process for internal cost projects
  • Generate settlement rule
  • Settle actual project
  • Perform the period end process for assets under construction projects
  • Settle assets under construction (collective processing)
  • Create assets for complete AuC settlement
  • Maintain settlement rule for final settlement
  • Perform final settlement of the investment project (collective settlement)
  • Monitor projects via project cost report

Benefits

  • Reduce maintenance work for direct settlement for each WBS element
  • Reduce likelihood of errors in settlement to profitability segments when characteristics to determine the segment are derived
  • Minimize inconsistencies (resulting from manual maintenance in the characteristic derivation for settlement to profitability segments) in complex customer projects with more than one settlement object

Where is Period-End Closing - Projects(BNA) being used?

This Scope item is used in the following way:

  • As a support function of Accounting and Financial Close within Finance Scope Item Group

Process flow of Period-End Closing - Projects (BNA)

Find below the process flow of the scope item Period-End Closing - Projects as it is defined for release s4hc-2111.


Download Process Flow of Best Practice scenario Period-End Closing - Projects (BNA) - S/4HANA Cloud
Ref: Finance of SAP S4HC-2111
Best Practices related to S/4HANA*1) Yearly Updates are released per September of each year
*2) The Quarterly updates are released per Februari, May, August and November
Details of future releases can be found in the SAP Roadmap section of each product. Go to SAP Roadmap Product Finder.
Knowledge Center Scheer Nederland | The Process Experts Visit also the SAP Cloud ERP knowledge center of Scheer Netherlands. The following topics are covered:
Place comment