The scenario enables the Order BOM processing type. You use this processing type if you want to make customer-specific changes to the BOM of a material that you configure in the sales order. The process supports a handover between sales order creation, order BOM preparation, and acceptance of those changes within the sales order.

Key Process Steps Covered

Sales order

  • Create sales order
  • Configure sales order item line (multilevel)
  • Switch to engineer-to-order process
  • Hand over to engineering

Order BOM handling

  • Create order BOMs
  • Configure sales order item line (multilevel)
  • Hand over to sales again

Sales order

  • Accept or reject changes of engineering

Benefits

  • Reduce order management cost by efficient, comprehensive support for fulfilling customers' special requirements, when using configurable products

Where is Engineer-to-Order Production with Variant Configuration(4R8) being used?

This Scope item is used in the following way:

  • As a core function of Production Operations within Manufacturing Scope Item Group

Process flow of Engineer-to-Order Production with Variant Configuration (4R8)

Find below the process flow of the scope item Engineer-to-Order Production with Variant Configuration as it is defined for release s4h-2021.


Download Process Flow of Best Practice scenario Engineer-to-Order Production with Variant Configuration (4R8) - S/4HANA OP
Ref: Manufacturing of SAP S4H-2021
Best Practices related to S/4HANA*1) Yearly Updates are released per September of each year
*2) The Quarterly updates are released per Februari, May, August and November
Details of future releases can be found in the SAP Roadmap section of each product. Go to SAP Roadmap Product Finder.
Knowledge Center Scheer Nederland | The Process Experts Visit also the SAP Cloud ERP knowledge center of Scheer Netherlands. The following topics are covered:
Place comment